Hi,
When i am trying to do settlement for project, system is throughing a error, error in allocation structure.
But when checked indetail..particular cost element need to be assigned in cost element group which is assigned in allocation structure.
But now my question system showing a Cost element which is inventory,but instead of invertory should be some expense element because i cannot maintain the Inventory cost element in cost element group.
From where the system is picking that Cost element.
regards,
Santosh kumar