on 01-19-2011 9:49 PM
HI Gurus,
Is there a way to setup 5 days or 7 days work Schedule on a single WorkCenter or capacity? Plz help
Yes, it is possible.
To do this, please change shifts in the work center capacity or change shifts in the capacity.
The shifts are defined in OP4A
Best regards,
Daniel de Assis Vieira