Hi Friends,

Tried to find out similar kind of question through this forum some how could not find out relevant to my requirement and hence posting.

I have an internal activity which assigned with WC1/AT1 (example, WC1 - Work center 1; AT1 - Activity type 1). Here we have already actual costs sitting on this activity throught CATS.

Due to change in business structure, few more WCs are added and few of the existing ones are deleted with activity types.

Then I have changed WC on activity from WC1 to WC2 and also Atype. Actual hours are again posted through CATS and no problem.

The issue is when we look at on confirmation screen, still I can see the old WC and AType. Then we have manually changed the WC and Atype on confirmation screen. Please note that new WC and Atypes are changed for those activities which does not have an actual costs. The only problem is not changing the WC on those activities whic have actual costs.

Any of my of you are aware of which user exit or OSS notes fecilitates auto change of WC and Atype on all the corresponding screens instead of manual intervention.

Looking forward hear from and thanks in anticipation.

Regards,

PSR