I have to load three cubes using process chains in a sequential order. The flow is in 3.X
ODS settings
Standard ODS
Activate ODS automatically
Update DataTarget automatically
This is the process chain I have implemented.
Start -->
Execute InfoPackage (Load Data to DSO) -->
DataStore data -->
Further Update of ODS data (Load Data to Cube)-->
Execute InfoPackage (Load Data to DSO) -->
DataStore data -->
Further Update of ODS data (Load Data to Cube)-->
Execute InfoPackage (Load Data to DSO) -->
DataStore data -->
Further Update of ODS data (Load Data to Cube)
When i checked the Process chain i got a warning at the process Further update of ODS data, before executing the second and third InfoPackage.
A type "Activate DataStore Object Data" process cannot precede process "Execute InfoPackage" var. ZPAK_8QNZS913OAO00J4TT9LTYEK9L in the chain
Message no. RSMPC013