Connecting dataloads through process chains?

34 Views

I have to load three cubes using process chains in a sequential order. The flow is in 3.X

ODS settings

Standard ODS

Activate ODS automatically

Update DataTarget automatically

This is the process chain I have implemented.

Start -->

Execute InfoPackage (Load Data to DSO) -->

DataStore data -->

Further Update of ODS data (Load Data to Cube)-->

Execute InfoPackage (Load Data to DSO) -->

DataStore data -->

Further Update of ODS data (Load Data to Cube)-->

Execute InfoPackage (Load Data to DSO) -->

DataStore data -->

Further Update of ODS data (Load Data to Cube)

When i checked the Process chain i got a warning at the process Further update of ODS data, before executing the second and third InfoPackage.

A type "Activate DataStore Object Data" process cannot precede process "Execute InfoPackage" var. ZPAK_8QNZS913OAO00J4TT9LTYEK9L in the chain