SNP optimiser, production cost calculation

115 Views

Hi

I have maintained 2 capacity variants for a resource; 01 with 8 Hrs and 1000$ cost and 02 with 10 Hrs and 1010$ cost. In the PPM for SNP, there is single level variable cost of 125.

Now in optimization run it is giving result as 390000$ for delay penalty and 6000$ as production cost. And is planning for only 8 hrs capacity. I think it should consider higher capacity to reduce non del charges so that total cost is less.. Is it correct?

Now if I keep single level variable cost as blank then production cost comes as 0. When and how will this cost in resource be considered.