Dear All,
I have some projects which is in released status & i want to change org parameter e.g. company code,controlling area,Business area,Plant & Profit Center @ project as well as WBS level
But in standard ,system will not allowed to change Org Parameter @ project as well as WBS level
I change Org parameter data @ table (PROJ & PRPS) level system allow me to do so
Please let me know is there any impact if i change org parameter data @ table level
Regards
Ravindra