Hi All,

How i can determine / derive the Release Strategy based on our own coding i.e via User Exit.

As my requirement is that we have 2 Service Items - > Based on first and second Service Item quantities the Release Strategy should be Derived.

For Example the Approval Limit for 1st Line Item Quantity is upto 1000 for Manager

upto 2000 for Director

the Approval Limit for 2nd Line Item Quantity is upto 5000 for Manager

upto 10000 for Director

For the Line Items the Approval Limits are Different

If Uses Enters in the 1st Line Item quantity 999

and 2nd Line Item quantity is 6000

then Release should go for Approval to Manager and Director.

Whichever is higher release it should consider that.

We are using Services ( Service Master for both Line Items ).

I know it is possible by creating 2 different document Type.

But how i can achieve in single document Type ( In Single PO )