Hi All,

I have two mixer M1,M2 and 4 packing line as P1,P2,P3,P4.In recipe M1 and M2 are primary and alternate in one operation,P1,P2,P3,P4 are alternate in another operation.

M1 is connected to P1 and P2,M2 connected to P3 and P4 in resource network in APO.

i have created order on P1 which is scheduling on M1 also. when i am moving the order from P1 to P3 in detail scheduling board system is not allowing.

Regards