Hi,

To get these result, i have done the following settings but still not able to solve the issue, the requirement is to create the single inspection lot for the several batches. For this I did

1. Batch Management for the raw material.

2. Tried different settings for the Control Inspection Lot i.e. 1, 2 and x as well, not tried Y as it is for GR against the prod order.

3. Then also maintain the Single result in the control indicator of the MIC of the material in inspection plan.

Beside these settings what the settings required to get the above result?

Please advise.

Thanks,