Hi Experts,
I have configured below settings for available capacity check,
1. In Order control for order creation / release (OPJK): "No check" indicator is not selected, Overall profile is SAPSFCG013 and Collective conversion field is "No creation if there is insufficient capacity".
2. In Production Scheduling Profile (CORY): Overall profile is SAPPI_G001, Confirm capacity indicator is selected and Finite scheduling indicator is selected.
3. In Scheduling parameters (OPUZ): Scheduling and Generate capacity requirement indicators are selected.
4. In work center, Relevant to finite scheduling indicator is selected.
When I check Capacity availability in process order, getting the message: Capacity available at all work centers
i have defined work center with finite scheduling and this work center has an capacity to produce 13 numbers in 48H.
And in master recipe also i have maintained for 13numbers 48H.
I created an Process order with current date scheduling for 13numbers . during this system shuould capacity is available at all workcenters..in this case no issue.
And i again crated the second order for 13numbers with current date scheduling, at this point according to me , the system as to show no capacity availabilty ..Finite Scheduling..but it is showing capacity is available in all workcenters.
..and i observed tn CM01.for 13numbers system is not taking 48H , it is showing Requiremmnt only 24hours..And also workcenter is overloaded..and y at the time of order creation system did not populated any message W C is overloaded..?
Thank u all i advance..