Hi all,

whenever I create inspection lot for source inspection (for PO) through Qi07, in the inspection lot, task usage assigned as a 6(goods issue), but i will assign 3 (universal) later on for the source inspection ( with respect to PO)in qa32 & later on i will proceed. But i want the system to assign the 3 (task list usage) automatically for all the inspection lots, how to enable the same?