Skip to Content
0
Former Member
Jan 16, 2011 at 07:07 AM

VA01,02 item level billing plan generate milestones Billvalue customisation

57 Views

Dear All,

In VA01 and VA02, when we are defining the Billing plan for an item, the bill value is the same as item value.

So when i generate billing plan for a year, the amount say 12,000 is applied for all billing plan items.

So net value = 12,000 * 12 = 144,000

In my case, while generating an annual billing plan, I want this amount to be divided for each billing plan item.

so for each item, it should be 12000/12 = 1000 rs for each month.

Ans net value should remain 1,000 * 12 = 12,000.

Please advice which User Exit or BADI to use and how to change the value in the billing plan.

Thanks and Regards,

Varun