Dear Guys
correct me if my understanding is wrong???
We can update the overhead to FG material through any one of the following
1. KGI2
2. CK11N
KGI2 - is for actual cost calculation and posted to Production order and settle the production order FG material
CK11N is plan cost of raw material and plan overhead cost calculated and updated in the FG material master through CK24.
Regards
Elangovan