Reg - MD04 MRP Element Pur Req quantity

405 Views

Hi,

I have a HAWA-Trading Goods material with details as follows:-

Lot Size: WK-Weekly lot size as per planning calendar

Lot-sizing procedure for short-term period u2013 P-Period lot-sizing procedure

Lot-size indicator for the short-term period:-K- Period lot size as in PPC planning calendar

Scheduling u2013 1-Period start = delivery date

MRP Type :- ZA- Auto. reorder point

MRP indicator of forecast - Not to be included in planning

Reorder Point - 2,965

Rounding Value u2013 72

Safety Stock -895

Service Level% - 96.

Procurement Type u2013 F.

In house Prod u2013 5 Days

GR Processing Time-2 Days

Planned Delivery Time in Days -77 Days

Planning Calender u2013 Tuesday Delivery.

Availability Check -02.

Total Replenishment Lead Time -5 Days

Total Available Qty(safety stock + All receipts) is 2031.

in MD04 screen MRP Element u201CPurRequ201Dgenerated is 72.

Can anybody explain me why is it generating 72.

If yes how the system calculates this 72.

Regards

Nilesh