Jan 14, 2011 at 01:27 PM

Stock in project

56 Views

Hi All,

At my client scenario we are using non valuated project stock and the requirement is as follows

Components are assigned under the activities under several different WBS Elements.

The project specific PR - PO and MIGO process will follow as normal.

When we do GR, the purchase price as a cost to be posted on respective WBS element but stock (quantities) needs to be generated under one WBS element (Header WBS Element)

Request you to please suggest the method by which I can achieve this. I am facing big problem while mapping this. Your inputs will be very much valuable to me.

Thanks and Regards,