one production order shows for cost element of cost of finished goods amt shows vey high the std price in material master is 71 and qty is 140 but it is not showing with this multiplication it is in lacs.
in the production order the target cost is zero and total actal cost in lacs and total variance percentage is 0 only but as per knowledge no variance know but if u calculate 140*.71 it should come less amt as per material maser but in production order i t shows high amount