Hello Everybody,
The material procurement and production scenario for project at my client's place is as follows
For example, project structure has four WBS Elements as WBS 1, WBS 2, WBS 3, and WBS 4
Material procuremet for production occures under Each WBS Element (Ex. Part A being procured under WBS 1, Part B procured under WBS 2 an Part C procured under WBS 3)
A finished product (BOM consists of Part A, B and C) is attached under WBS 4 and production order is triggered for the same under WBS 4
Requirements -
Should able to do GI to production order from WBS 1, 2 and 3
After MRP run on finished product, system should consider the stock available under WBS 1, 2 and 3 and not generate the PR again (shoul not duplicate PR)
Request you to kindly give valuable inputs
Thanks in advance
Regards,
Parimal