Hi,

We're having issues with cost not rolling up to WBS / project level in hierarchy reports like CN41N and CN41. This issue is happening on projects settled to WBS element, network, or order (due to 'internal business volume' mechanism). To overcome this issue, we're planning to assign settlement cost elements ONLY to value categories in CJVC (right now both settlement and debit cost elements are assigned to value categories in CJVC).

We're bit worried that if we do this change (of assigning settlement cost element only to value categories) whether it's going to affect areas other than PS hierarchy reports. Do you know whether this affects other areas like finance, etc...?