Hi,
I have multilevel BOM (almost 10 levels with around 1500 materials), in which many materials repeat at different levels.
I am facing problem in one of the material during MRP, This material is used at 10 different levels. Altogether to produce a FG it requires in 36 numbers. In different levels quantity of it required is different. Say 8,1,4,2 etc but total qty is 36.
When MRP is run the requirement generated for this material is same at all levels i.e 36(total qty) / 10 (BOM levels) = 3.6
But actually system must generate requirements as per BOM quantity. Not sure what is wrong.
Requesting you all to reply quickly for this issue.
Regards,
Pavan