Dear All,
I have created Production order, BOM, routing, work center and related costing with costing sheet.
1. costing sheet is attached with PPC1 and PPP1
2. In costing sheet -> Quantity based overhead rates in configured for which overhead group is defined and assigned with the material master in costing view.
3. Production Order is released and actual confirmation is done.
4. CK11N run --overhead is not calcuated.
5. then run KGI2, the status is showing without any error - overhead is calculated but in the Debit view, the screen is blank.
I really confused.
Kindly help to solve this issue.
Thanks in advance
regards
elango