Hi Gurus,
Currently, we are facing an issue that the batch master was created wrongly in the following process:-
STO > Goods Issue of Mat A - Batch 1234 from Plant A > Goods Receipt of Mat A - Batch 1234 to Plant B
Batch 1234 -Plant A
Production Date: - 02.04.2010
Shelf Life Exp. Date: - 15.05.2010
During GR into plant B, we noticed that the batch master is created with wrong data:-
Production Date was copied wrongly into Shelf Life Expiration Date. Whereas the Shelf life Expiration Date become the production date?
Batch 1234 -Plant B
Production Date: - 15.05.2010
Shelf Life Exp. Date: - 02.04.2010
May I know this happened? Hope to get advice from you all. Thanks!