Dear All,
I am trying to create a maintenance order from IW31, the problem is if i create the order and give the priority on the main screen i.e. header data tab, system does not change basic start and finish date, but if i give piority on initial IW31 screen system does change basic start and finish dates according to priorities. In notification these priorities are working fine.
Any clue if i am missing some thing in configuration. I have tried all the scheduling parameters as well.
Thanks
Rana Adeel