Dear Expert,
We have a scenario in subcontracting wherein the sales order the customer also wants to see the components and as such along with the Header item of subcontracting ,we also mention the components as another line item in the sane Sales Order.
Now from the sale sorder two Po's are created onr for the subcontractor and one for the compnens to be procured.
Since the components are procured on sales order stock there is noway we can issue it to the Vendor stock through Movt .Type 541.
As per SAP AG WE CAN:
"ubcontracting is also possible in conjunction with sales order stocks and project stocks. The subcontracting orders are account-assigned to a sales order or a WBS element. Thus, the components are not transferred (using a transfer posting) to the u201Cstock of material provided to vendoru201D but are directly withdrawn from the sales order stock or the project stock at the time of the goods receipt. The material manufactured is also posted to the sales order stock or to the project stock. The cost of subcontracting is then debited to the sales order or WBS element.Since the components are not transferred to the u201Cstock of material provided to vendoru201D, we recommend that you use a transfer posting to transfer the provided components to a new storage location (for example, 9999). This enables you to obtain an overview of those stocks that are physically located at the subcontractor.This information is particularly important when you carry out a physical inventory of the sales order stocks and project stocks."
But my query is that how many such storage locations will be created for the subcontracting vendors.
Secondly for the stock transfer from sales to storage location , we have lots of sales order, is dera way through which we can do bulk transfer rathar than clicking at new item everytime and then doing the transfer posting.
your expert advice shallbe helpful in resolving a longtime pending issue , waiting for the response.
Regards
Jabeen