Hi guru,

I have encountered this problem when i'm trying to convert a planned order to production order. This is a make-to-order (MTO) scenarion

I have configured a make to order situation. Material master

strad grp = 25, MRP = PD, item cat= 0002

Running mrp md50 creates planned order,

however once i trying to convert it to production order, there is error message which is "No valid task list for material in XXX plant XXX for sel.criteria"

I have create a normal bom and routing using Ca01 and cs01. May i know what's wrong with this error. Need help urgently.