My client having following query---
He has created 3 sales orders for one ROH say 1 no sales order is having 100 qty, 2 no SO 100 QTY, 3no SO 100 qty. When MRP happen system generate 3 different pru2019s for each sales order but my client need only one collective pr of 300 qty u2026
How to do this...?
Arun
Maintain a Lot size as "MB" Monthly Lot size or "TB " Weekly lot size in MRP 1 view, and maintain Individual/Collective indicator as 2- collective indicator.
When MRP runs, system will combine the requirement with in the period maintained in Lot size and give Single PR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Is the dependent requirement lies with in the period ( as mentioned in Lotsize) , If you maintain MB, system will conmbine the reqmt and give the single PR with in the month, IF you maintain TB< system will combine all the dependent requirement with in the week and give the single PR for a week.
I Apologize for that , I think the material is procured material for In house prdn, I haven't read that line.
Since the material is trading Material, When the order comes, system will post the reqmt as sale order requirement, while running system will plan the Material based on sale order, you can combine it,
During MRP system will consider 3 PR only if you want sale order reference also in procurement
If you want you can assign the 3 PR into Single PO, If the vendor is same
If you don't want sale order reference in procurement then
Or Use strategy 40 for that material, Check while creating a sale order requirement type is KSV, and Lot size MB, While running MRP system will create a Single PR for your requirement
Edited by: Sundaresan . E. V on Jan 12, 2011 1:16 PM
Hi,
To fix the issue you have 2 options:
1. Use stg. grp - 40, then change the rqmt type in SO from ZE to KSV. Do this only if its acceptable for the business & all scenarios are tested. Then re-run MRP.
2. Make a copy of lot size MB to say ZB in OMI4. Then for field Lot Size SOP maintain value 2. Then assign this lot size to the material & re-run MRP with planning mode as 3.
Good luck.
Regards,
Vivek
Arun,
Thanks for the screenshot. Please see my comments below,
1. Though there are same PN's used in different SO's , after procurement the stock will come under Sale order stock not unrestricted. So the cost which occur for procurement will arrive for the particular SO.
2. Your client is asking you to combaine all requirements in one PR in order to create one PO for all the requirements (May be). In this case you can suggest the client to combaine 3 different PR into one PO.
You can't combaine 3 PR Qty's into one PR.
Regards,
Sundhu
Thank u... Sundaresan/Vivek...
Problem has been resoled.
Arun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi experts,
Jiaul Haque/Sundaresan . E. V/Prasobh Karunakaran/ Dogboy49/ R Brahmankar..
Any solution for this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Arun,
My suggestion to create one Sale order with three line items if the customer is same. Also what strategy you are using?
If its Make -to-order then give collective requirements in Material Master data.
Check and revert back.
Regards,
Sundhu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.