Problem in Sub-contracting receipt

Former Member
0 Kudos

Hi Experts,

I have created a SC PO, did 541, and while doing GR (took stock type quality inspection) for final product system does post the 543 movement type for this GR, please advise what to be done?

Is there any thing missing from quality side?

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

Which Mvt is used to GR 101 or 103 at the time of 103 no a/c will be generated it will only generate at the time of 105

because 543 is automatic mvt, that will consume the material, also check your BOM and Sub Contracting PO, if the same is picking up correct

Regards

Niti Narayan