Hi, we are having a strange system behaviour.
- 3 sales orders are created for a material.
- At the time when order is created, available stock quanity in SLoc is zero. So the user selects the delivery proposal date given by the system (for this material it is 30 days - say 11 feb 2011).
- So in each of the three order, we have 2 schedule line. One for todays date (which is not confirmed) and the other for 11 feb 2011 (which is confirmed).
- Now partial (qty) stock is made available in SLoc ( stock is in unrestriced use)
- When Av. Chk is done in one of the above order, system does not propose the partial available qty.
- However, if Av Chk is executed for all the 3 orders (and the orders are saved), available qty is proposed for confirmation in the last order for whihc av. chk was done. Ideally system should have proposed these qty during av. chk in first order itself. This is strange behaviour in production system, but it is working fine in quality & pre-production.
Please guide n how to trace & resolve this issue.