hi all,

i hav a BOM for Finished material, for e.g.

Finished100 (MRP-PD, Strategy-20, Proc Type-E)

-->Semifinished100 (MRP-PD, Strategy-10, Proc Type-E)-->Raw100 (MRP-PD, Proc Type-F)

----


>Raw101 (MRP-PD, Proc Type-F)

--> Raw200 (MRP-PD, Proc Type-F)

-->Raw300 (MRP-PD, Proc Type-F)

1. I create a Sales Order for Finished100.

2. When i run MRP for this material MD50, it ask Next stopping point, i select "Proceed without Stopping" & then saved the results.

3. In MD04 i open order structure for planned order finished100.

it show only two Planned Order Created for Finished100 & semifinished100, as per requirements.

Also system creates DepReq for all Semifinished & Raw Materials.

4. But system is not generating any Purchase Requisitions for RAW Material.

though i hav selected Create Purchase requsition as '1' in MD50 in MRP control Parameters.

please help...where i am missing....

thanks in advance.

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Solved.

Former Member
0 Kudos

Solved...

Maintained individual requirment & strategy 20 for all raw material...

now prs generated thrugh MD50.

Thanks.

former_member467138
Active Contributor
0 Kudos

Hi,

Your raw materials are collective item so that PRu2019s are not generated when u run MD50.

If u want PRu2019s

1) MRP run by MD02

2) Change requirement type collective to individual.(Pl note that SAP will not suggest again and again changing requirement

type of material.)

3) Configure the explosion type for BOM as individual in SPRO-PPu2014BOMu2014ITEM DATA-DEFINE EXPLOSION TYPE- Create new one and donu2019t active any field only put 1 in field of I/C.

Arun

sundaresan_velayudam
Active Contributor
0 Kudos

Dear

In MD50, System will Plan only Sale order Requirement,

Since You are procuring a Raw material NOT with respect to sale order, Thats the reason in MD50, system not creating a PR for Raw material

IF you want to plan up to Raw material use MD02

IF you are Procuring based on sale order reqmt, then Maintain Individual requirement in MRP 4 view for finishr material, semi finished & raw material

and then Run MRP in MD50

System will plan for Raw material also with reference to sale order

Since You Have maintain Individual reqmt in MRP 4 view for finish material and semifinish , system create a Plan order with reference to sale order

Former Member
0 Kudos

have you checked the stock of the raw material in MD04?