Hi,
When I try to create a Network and put the start date I get an error message-
Date 01.01.2011 is later than the validity period of the factory calendar
Message no. CO032
Procedure
Enter a date which lies within the validity period of the factory calendar.
And this does not allow me to cfreate the network.
But the same date is accepted by the system for WBS element and activities.So I doubt it has anything to do with the factory calendar.
Please assist.