Factory Calender

76 Views

Hi experts ,

While doing MIRO we are getting error message as the date lies after factory calender "01" (valid upto 2010). I checked the concerned plant to which factory calender "IN" is assigned (valid upto 2025). Still do i need to extend factory calender "01"

I refered the earlier threads on Factory calender which reccomends to update the calender Buffer in SCAL, will this solve the purpose if I refresh it in running Production server. pls guide me on the same.