hi i am having trouble generating cost for activity labour
getting a message while running costing "Missing formula in work center"
our CO personel has created a activity labour and done all the settings in kp26
in work center i have given
sap0
sap008 in capacity tab,sap004 in scheduling tab
in costing tab given activity labour which was created and in formula given sap003-because sap008 is not being assigned .
Where could be i going wrong
have checked previous post nothing there.