I am using SAP ECC for execution, and SAP APO SNP heuristics for planning.
So, for a product planned in APO, the MRP type in ECC is X0.
So, as there is no MRP planning in ECC for such a product, what is the use of the ECC planning time fence? I think it becomes redundant in ECC - yes? In fact, I do not see it in the stock reqs list (MD04).
So, in ECC, all that 'planners' can do is to manually reschedule planned/production orders - yes?
Any shortage alerts will only be visible in APO - yes?
Thanks for any advice on this...