Hi All,

I have a problem and I need some help. My plant A is REM. The Finished Goods material "XXX" recieves the requirment from the Customer as on Schedule line. Now the backward scheduling is done based on delivery date in schedule lines.

The requirment is that irrespective of plan order quantity, The inhouse production time must be 10 Days. Which means that I must have 10 days time between Scheduled start date and scheduled finish date.

Please help me. EVEN If I maintain the inhouse production time in MRP 1 view in material master, it is not considered in planning.

Please gine me some solution how to make it happen. I need some immediate solution.