cancel
Showing results for 
Search instead for 
Did you mean: 

Planning iin REM.

Former Member
0 Kudos

Hi All,

I have a problem and I need some help. My plant A is REM. The Finished Goods material "XXX" recieves the requirment from the Customer as on Schedule line. Now the backward scheduling is done based on delivery date in schedule lines.

The requirment is that irrespective of plan order quantity, The inhouse production time must be 10 Days. Which means that I must have 10 days time between Scheduled start date and scheduled finish date.

Please help me. EVEN If I maintain the inhouse production time in MRP 1 view in material master, it is not considered in planning.

Please gine me some solution how to make it happen. I need some immediate solution.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

Run MRP with scheduling indiactor as "1" in MD02, then it will consider inhouse production time and not thee time from routing.

But this time will be independent of lot size , whenther u produce 100 or 10000 , it will plan for 10 days only.

Amit