Hello ,

We are using Direct procurement scenario ,During MRP run we generate a Plan order(which have dates); which converted into Production order later.For these production order material is needed (components). And for procuring components we need to create purchase order.

Assumption :- Each component have same Procurement lead time

Our requirement is Purchase order and GI in Production order should be done sequentially, means Based on Production order date ,FIFO based Purchase orders are created and GI done in Production order. Production order with earlier production date have purchase orders earlier and we do GI in production order accordingly.

Kindly suggest

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

According to your scenario, all components should be procured individually for each production order of the final product. It means that for each production order, purchase orders for its components is created.

What you describe should be the standard behaviour of SAP .

Please, If I am wrong, provide more information.

Regards

Former Member
0 Kudos

Hello Dario

Thanks for your reply. Our requirement is to put a check on system that GI for production order should be done FIFO wise

means as MRP generate 3 production order of same material each at different date , we want issance of components to be done on FIFO wise in production order

Regards