Maintenance Plan Call Date

1160 Views

Dear Expert,

We have done the setting for performance base maint. plan for our fleet. The all controll parameter is as follows

Shift Factor Late Compl. 100 % Call horizon 100 %

Tolerance ➕ 10 % SchedPeriod 365 DAY

Shift Factor Early Compl. 100 % completion requirement is activated

Tolerance ➖ 10 %

Cycle modification factor 1.00

Cycle frequency every 6000 Kms

Counter annual estimate 36000 Kms

the planned counter reading is 136414 Kms but the user have techo the order on the counter reading 138410 by date 05.01.2011.As per our setting the next plan couter reading would be 144410 Kms. & got the same correctly as shown in ip10.

But the problem is when we schedule the maint. plan through IP30 on dated 05.01.2011 after completion the previous order, Next order immidiately release on the counter reading 138463 by the proposed date 06.03.2011 while as per our experiance, it should be appear after reaching the targeted counter reading (144410). All order automatically released on their due dates.We have also updating the couter on daily basis.

Can any body clarify the problem so that we can run the process smoothly. Priority should be appriciable.

With Warm Regards

Mohammad Khalid