Hi, we are facing an error situation that when we try to release production order there came an issue that few component committed quantity is less than required quantity. When we check the stock of the components they were having enough stock to consider for this production order.

What could be the other reasons or cause for this situation. Can any one suggest for the correction action.

would reservation cause this problem when i check the component availability overview it has ATP 0. will it cause this.

When i look in to the system there were several Orders that were in CRT state that were using same components as used in the current order under discussion.