issue in committing material for production order

Hi, we are facing an error situation that when we try to release production order there came an issue that few component committed quantity is less than required quantity. When we check the stock of the components they were having enough stock to consider for this production order.

What could be the other reasons or cause for this situation. Can any one suggest for the correction action.

would reservation cause this problem when i check the component availability overview it has ATP 0. will it cause this.

When i look in to the system there were several Orders that were in CRT state that were using same components as used in the current order under discussion.

Edited by: kkr_chandran66 on Jan 6, 2011 3:16 AM

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 06, 2011 at 03:03 AM

    Hi,

    Use CO09 report to check the demand & supply status. There might be stock, but as you mention, the same could be committed to other orders.

    So if you want the available stock to be commited for your order, you can use CO06 to change the commitments manually or you can use COMAC with 'Reset Availability Data' check box ticked. System will then commit as per selection made.

    Once the commitments are done you may proceed to release the order.

    Hope the above steps are clear, but If you need any further assistance, revert.

    Regards,

    Vivek

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jan 06, 2011 at 04:00 AM

    Chandran,

    Yes, if your availability check scope is defined to check including order reservations/reservations then system would not able to commit due to already reserved quantity.

    If the already created orders are no longer going to be used than set the status of these orders t TECO. If its required as explained by Mr. Vivek you can do backorder processing/availability check.

    Regards,

    Prasobh

    Add comment
    10|10000 characters needed characters exceeded