error "Activate ppm or remove it from model"

Hi when w eran netwrok heuritic we got errors stating " Planning object could not be determined" From the message I found that some PDS are missing.

Then I ran the TS_LCM_CONS_CHECK and found the same thing .The message that I got is "Activate ppm or remove it from model"

But when I checked the PDS does exist in SCM SNP. Can anybody help me in trouble shooting this

Thanks !!!

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Jan 07, 2011 at 11:15 AM

    Hi

    Can you please check if you also have created PPM for any products in APO by T-code /SAPAPO/SCC03 - Production Process Model . As the error shows Active PPM and as per explanation you were checking PDS.

    Please also check SAP note : 385602

    It might be there is some conflic. Please let us know if it help you.

    Thanks

    Amol

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      NO PPM is not created for any of the material loc that I am testing... in consistency check it says ppm/pds so by ppm its meaning pds,,,,

      also i tested by changing the procurement type to external procurement in product master then i dont get that error in heuristic run...

      in curto_order_explode i get the message that the material is not in an active integration model....but when i checked in ecc its there in active integration model...so I generated and rimodini that plant again....but still teh problem exists with the heuristic run

  • avatar image
    Former Member
    Nov 14, 2013 at 01:17 PM

    Hi Siva,

    I had the same problem. Please check SAP Note 1631566.

    Add comment
    10|10000 characters needed characters exceeded