Phase Overlap in SAP PPM Project

Dec 08, 2016 at 06:38 PM

48

avatar image
Former Member

Hello Experts,

We have a scenario in PPM Project in which we need phase overlap in scheduling. Currently system takes 2 phases in Pred-Succ mode. Can BADI DPR_SCHEDULING solve this issue?

Experts please help!!!

Nachiket

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Judith Gabriel
Dec 14, 2016 at 03:27 PM
0

Dear Nachiket,

you can use BAdI DPR_SCHEDULING with method STRICT_BOTTOM_UP to allow overlapping of phases.

Information can you find under "solution" in SAP Note 1150146.

Best regards,
Judith