Hello Experts,
We have a scenario in PPM Project in which we need phase overlap in scheduling. Currently system takes 2 phases in Pred-Succ mode. Can BADI DPR_SCHEDULING solve this issue?
Experts please help!!!
Nachiket
Dear Nachiket,
you can use BAdI DPR_SCHEDULING with method STRICT_BOTTOM_UP to allow overlapping of phases.
Information can you find under "solution" in SAP Note 1150146.
Best regards,Judith