Phase Overlap in SAP PPM Project

Hello Experts,

We have a scenario in PPM Project in which we need phase overlap in scheduling. Currently system takes 2 phases in Pred-Succ mode. Can BADI DPR_SCHEDULING solve this issue?

Experts please help!!!

Nachiket

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Dec 14, 2016 at 03:27 PM

    Dear Nachiket,

    you can use BAdI DPR_SCHEDULING with method STRICT_BOTTOM_UP to allow overlapping of phases.

    Information can you find under "solution" in SAP Note 1150146.

    Best regards,
    Judith