Skip to Content
0
Former Member
Jan 04, 2011 at 12:34 PM

PO release strategy change after ME22N

371 Views

Hi All,

Is it possible to trigger a new release strategy when a PO is changed in ME22N?

For ex

When PO value < 5000 INR , only buyer B1 releases after the PO is created , if the same PO is changed in ME22N and the PO value is raised to 5500 INR , then new strategy should be triggered then the release is as follows,

B1 - Buyer - First release

M1- Manager - Second release

V1 - VP - Final release

Please let me know how to achieve this in SAP

Thanks

Benny