Dear Forum,
While creating a resource (CRC1), we are choosing the Standard value key in Basic Data tab as "YPH3" for "Process Manufacturing (6 Keys)". The problem is that we are entering the standard timing for some activities which are only performed in the 1st batch of the campaign like set up time and cleaning time. This is affecting our ability to have a standard timings/cost for our products since these timings will be calculated for all batches in the campaign. Our campaign size is variable according to the market demand.
Anyone have a suggestion to solve this issue.
Thank you,
Fadi