on 01-04-2011 8:04 AM
Dear all ,
We are using make to stock scenario and for planning using PIR tcode md61 .( product group wise )
In the same fashion can we enter the SOP or
1) how to enter the SOP for product group
2) Any report to Display the SOP entered ?
pl guide
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
To enter SOP for product group -> MC81, to change -> MC82 & to display -> MC83
To transfer SOP for product group to demand mgmt. use MC75
Hope it clarifies.
Regards,
Vivek