Former Member
Jan 04, 2011 at 08:03 AM

reg Process mfg.

28 Views

Hi All,

Here food manufacturing industry , we are using 40 stratergy ,

For Eg, They can producing 8 lots per shift , In recipe im giving 1 day for 8 lot ,

Im runnig mrp system calculating that dates is correct , but if im giving 4 lot system is giving 0.5 days but in real they need 1 day for producing 4 lots also because of process industry

please suggest me to solve this,

thanks.