Hi All,
Here food manufacturing industry , we are using 40 stratergy ,
For Eg, They can producing 8 lots per shift , In recipe im giving 1 day for 8 lot ,
Im runnig mrp system calculating that dates is correct , but if im giving 4 lot system is giving 0.5 days but in real they need 1 day for producing 4 lots also because of process industry
please suggest me to solve this,
thanks.