dear experts,
what exactly he want is if the price of the material is 0 zero , it should not be allowed to be issued against a production order.please tell me if we can do with configuration which is the best way or else we have to use any exit.
if we use exit we will check in MBEW table and field verpr, if the verpr field value is 0 zero then we will not allow else we allow the material to be issued.
regards
krishna mohan