I have come across a capacity planning scenario in metal industry.
Suppose the machine is producing sheets of thickness ranging 2mm thickness to 8mm thickness. There are three groups as shown below P, Q, R,
These individual product orders are loaded on Resource: W100
Groups Limited Capacity In Tons Individual products Planning product
Group P: Less than 2 mm 75 a1, a2, a3, a4, a5 P
Group Q: From 2mm to 4 mm 100 b1, b2, b3, b4, b5 Q
Group R: From 4mm to 8mm 325 c1, c2, c3, c4, c5 R
The total sheets produced in one day 500.tons All the groups should be producced on daily basis in the sequence of P,Q,R. Limiting the capacity given above. In SNP planning , I would to limit the capacity based on the basis of planning products.
The planned orders will be coming for Individual products that are a1, a2, a3, a4.
In SNP planning run, the quantity of Individual orders should be sum up at the group level.
For Group P : a1, a2, a3 u2026. Sum up and the quantity should be checked for Capacity of 75 tons order quantity.
For Group Q : b1, b2, b3u2026. Sum up and the quantity should be checked for capacity of 100 tons order quantity.
Like wise for Group R : c1, c2, c3u2026. Sum up and the quantity should be checked for capacity of 300 tons order quantity.
I want to use the planning product concept to model this scenario. P will be the planning product for a1,a2,a3....
Q will be the planning product for b1,b2,b3....
Following master data created : Material master , BOM , routing for individual products. Material master for planning product. Planning product updated in the material master of individual products in MRP view.
Please let me know , your suggestions for use of planning product scenario with capacity check on product group level.
Waiting for your reply.