Customer pick up the goods from plant

In SNC (5.1) we get the delivery date for firm receipts on web UI . This is based upon the transplantation lane which has transit time. For eg 4days i.e. 96 hrs.

Now the issue is sometimes customer pick up the material directly from plant.

How this scenario should be handled since customer picks up the material directly from Plant and in SNC we can see the delivery date means material availability date at customer which is after 4 days?

Thx

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    avatar image
    Former Member
    Dec 30, 2010 at 09:07 AM

    Hi Vaibhav

    If you define transportation distance and duration as zero in transportation lane.

    Then system proposes the ship to date and delivery date same.

    You can manually edit this field and set the delivery date.

    But how frequently does the customer picks the orders from plant???

    else you can use two means of transport one product specific with trnsp duration zero and the other with duration.

    Depending on the need basis you need to manually change the means of transport in webui

    Best Regards

    Vinod