Hi PM Gurus,
I am working with performance based preventive maintenance (every 5,000 Kilometer based).
I created counter and assigned to the equipment and maintenance plan is also created with initial reading 6,000km.
First I run IP30 and I got maintenance order. But again I run IP30 this time also system given the maintenance order actually the second order should come after 10,000 only, bcz my strategy is every 5,000km.
What will be the mistake during IP30 run.
My requirement is system has to create the order every 5,000 km reached based on measuring document entry.
Thanks in Advance.
Regards,
S.Babusingh