Dear All,
I have a multi-level product structure, FG takes 10hrs for 100pcs (in Routing), whereas SFG takes 6hrs for 100pcs.
Now if I maintain a PIR of 100pcs for FG and run MRP, the planned order for the two in-house manufactured materials (FG and SFG) has production dates as below:
FG: Start 31/12/2010 18:45 & Finish 01/01/2011 06:00 (there is 75min break in between the start and finish time, so this is ok)
SFG: Start 30/12/2010 22:00 & 31/12/2010 06:00 (there is 120min break)
Now the query is that what setting I need to do such that the Finish date of SFG is same as the start date of FG, i.e. in the above example the Finish Date of SFG should be 31/12/2010 18:45 as against 31/12/2010 06:00.
Thanks,
Ravi