Hi,

We are using alternate sequences in routing. Can you tell me how to transfer alternate sequences to alternate modes in SNP PDS.

Only one mode per activity is created when we transfer SNP PDS, however we could transfer PP/DS PDS with alternate modes.

We don't want to use resource classification in ECC.

Thanks,

Andy

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Dec 22, 2010 at 04:53 AM

    Hi,

    From an integration point of view there are basically two ways to create alternative modes in APO, these are resource classification and alternative sequences.

    Alternative sequences in the routing are transferred as alternative modes. The prerequisite is that the number of operations is the same in each alternative sequence u2013 if necessary, dummy operations have to be included. As described in note 357178, for the PDS it is however required to implement the BAdI CHANGE_EWB_STRUCTURES. For the PPM the user exit CIFPPM01 has to be implemented (see note 217210).

    Thanks,

    nandha

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Sravan,

      Thanks for your reply. I have two alternate sequences tied to primary work center, but only one SNP PDS is created, but I could transfer PP/DS PDS with 3 alternate modes. We applied a note to make this work in PP/DS.

      If it is a standard behaviour, where am I going wrong?

      Also what do you mean by saying - "Though you achieve the required by doing some enhancement"? Would you please provide more details.

      Thanks,

      Andy

  • avatar image
    Former Member
    Jan 03, 2011 at 06:19 AM

    HI Andrew,

    SNP doesnot support alternative modes. it is only supported in PPDS. SNP PDS supports secondary resource which can be used to constrain the available capacity of the primary resource with some other dependent resource.

    Regards

    Vaibhav Sareen