I have certain requirement in reports. We create all the activities with certain amount of work and duration in a project. Then we schedule the whole project.

Now my requirement is , I have to get a report where in I can get weekly(current) and monthly (current)planning. I believe no standard report gives this output, if I want to develop how I would give the logic

Regards,

Laxminarsimha

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Dec 20, 2010 at 09:37 AM

    Hi

    By weekly & Monthly planning are you looking only at the cost?

    If that is so, you can use logic of the Period break down option of CNS41 report.This option provides you the monthly report but in the cummulative fashion.You can chage the logic for discrete amount.

    For weekly report you have to build a logic on the Scheduled dates as this Monthly report will be based on period values.

    Regards